Croton Dam
The southern shore of the Croton
River at the point where the dam
is located, is a gneiss rock;
moderately sloping up the hill
from the water's edge; but not
appearing to extend far into the
river. The dam required to be
raised forty feet above low
water in the river; and it was
an important object to arrange
the plan, so as to obtain a rock
foundation for the masonry.
To effect this, the northern
abutment was located as far in
the river as the rock was
supposed to extend, and from
this to build up the dam to the
level where the top line
intersected the natural slope of
the hill, and then to cut the
hill away; making an opening
sufficient for the waste weir of
the dam.
In prosecuting the work, it was
found that the rock descended
more rapidly into the river than
was supposed, which induced the
moving of the abutment further
towards the hill than at first
located; and finally, an
artificial foundation had to be
made for a small portion of it.
It was intended to make the
waste of the dam 100 feet, with
abutments of eight feet high;
but in consequence of the
disappointment in regard to the
extent of the rock in the river,
it was found difficult to obtain
the desired length of water-way,
and it was concluded to raise
the abutment to twelve feet at
the lower end, and fifteen feet
at the upper end, and allow the
water-way to remain an average
length of ninety feet for this
height. The natural rock formed
the southern abutment, and the
aqueduct being on this side, the
water was conducted to the
gateway, at its head, by a
tunnel, cut 180 feet through the
rock; this allowed the gateway
to be located on solid rock, in
a situation not exposed to the
floods of the river. The water
enters the gate-chamber by an
archway through the second
bulk-head. The gate-chamber is
provided with a double set of
gates; one set of guard-gates,
of cast iron, set in cast-iron
frames, and one set of
regulating gates, made of gun
metal, set in frames of the same
material; the gates are all
eighteen by forty inches, and
there are nine gates in each
set. They are all operated by
means of wrought-iron
screw-rods.
The gate-chamber and bulkheads
are constructed of well-dressed
masonry, laid up in hydraulic
cement.
In the north abutment a waste
culvert has been constructed,
with suitable gates of cast
iron, to draw the water down in
the reservoir, at such times as
it may be necessary, to
facilitate the making of any
repairs that may be required and
to discharge the river at
ordinary times during the
construction of the work. From
this abutment the old channel of
the river was filled by an
embankment, with a heavy
protection-wall on the lower
side, which was raised fifteen
feet above the waste weir of the
dam, and designed to be fifty
feet wide on the top, but was
not completed the full width
when the unprecedented flood of
January, 1841, carried it away.
The embankment stood well, and
gave no indications of failure,
until the water rose to near the
surface, and passed through
between the frozen and unfrozen
earth about twenty inches below
the top. After the breach was
made in the embankment, large
masses of heavy ice came down
from the reservoir, which soon
broke down the unfinished
protection-wall, and carried off
nearly the whole embankment. The
masonry of the dam and abutment
sustained but little injury.
Such a flood had not been
anticipated, and the watery-way
proved insufficient to pass it
off. Had the embankment been
completed the full width, and
the protection-wall carried up
to the full height it was
intended to carry it, the work
might have proved adequate to
the emergency. It was determined
to fill the gap made by this
breach (about 200 feet long) by
a structure of hydraulic stone
masonry, adapting 180 feet as
waste weir. This work presented
all the difficulties it was
originally intended to avoid, by
carrying the work partially into
the hill. It was necessary to
form an artificial foundation,
and carry up a heavy body of
masonry in the channel of the
river, which, in some parts, had
fifteen feet in depth below its
ordinary level, subject, in
ordinary seasons, to frequent
and sudden floods, and affording
no means to form another channel
for it to pass, until the work
could be accomplished.
Had it been admissible to
construct the dam with timber,
the difficulties would have been
far less. But the importance of
the object it was designed to
secure, and its great height,
demanded the most permanent and
durable structure that could be
made.
The greatest height of the weir
of the dam is forty feet above
the low-water level, and
fifty-five feet above the bed of
the river. The width of masonry,
at low water line of river, is
sixty-one feet.
The form on the lower face
commences on a curve, described
by a radius of fifty-five feet,
and continues to within about
ten feet of the top, when a
reversed curve, on a radius of
ten feet, carries the face over,
and meets the back line of the
wall. The back line is carried
up vertically with occasional
off-sets. The main body of the
work is laid up of rough stone:
the curved face of large and
closely-cut stone, with four
heavy courses at the bottom,
dovetailed together, the joints
cut to the line of radius of
curve.
Above the masonry an embankment
of earth is filled in, and
extends to 275 feet in width on
the bottom, with a slope of one
to five on the up-stream face.
The north end of the new weir is
terminated by an abutment that
rises twelve feet above it. From
the toe of the masonry an apron
is extended thirty-five feet,
composed of hewn timber secured
by ties, bolts, and tree-nails,
in a very substantial manner,
and filled, for sixteen feet
from the stone work, with
concrete masonry, and the
remainder with loose stone, and
covered with a course of six
inch white elm plank. A second
apron is partly made, which is
to extend thirty feet further.
At 300 feet below the main dam,
a second dam is in progress,
which is to be nine feet high,
constructed of timber, stone,
and gravel, which will set the
water back over the apron of the
main dam, and form a pool to
check the water as it falls on
it.
A coffer-dam was constructed in
the river to enclose about 120
feet of the work, from which the
water was pumped by a
steam-engine, and a concrete
foundation laid down on a very
firm hard pan. The remainder of
the foundation was made by
sinking timber piers at suitable
distances, running parallel with
the dam, and filling the spaces
between them with concrete
masonry. In preparing the
specifications for this work,
the method and order of
prosecuting it, were
particularly designed, and from
which no material departure has
been found necessary; the
structure is now nearly
completed.
The contractors, Messrs.
McCullough, Black, McManus and
Hepburn, have evinced a highly
commendable energy and ability
in its prosecution.
This dam sets the water of the
river back five miles, and forms
a reservoir of about four
hundred acres, and has rendered
it necessary to construct
several new roads and bridges as
a substitute for those covered
by the flow; the principal of
which is the Somers town
turnpike. The grounds lightly
flowed on the margin, have been
excavated so as to give four and
a half feet for the least depth
of water. From this reservoir
the water flows into the
bulkhead, at the upper end of
the tunnel, from a level
averaging ten feet below the
surface.