The concentration of business at
the lower end of Manhattan, and
the development of the district
across the East River for
residential and later for
business purposes, caused
attention to be given at an
early date to the matter of
better transit facilities in
that direction.
A proposition to build a chain
suspension bridge over the East
River, with a BROOKLYN clear
span of 1,500 feet and a length
of 2,100 feet between the "toll
gates," was proposed as early as
1829. The structure was to have
been 28 feet wide, the height of
the granite piers from the water
line to the roadway 160 feet,
and from the roadway to the
extreme point of the pier 65
feet. This and similar schemes
came to naught, until, in 1867,
the Legislature passed an act
incorporating the New York
Bridge Company. In May of that
year John A. Roebling, who had,
by designing and erecting the
great Niagara Suspension Bridge,
earned a high reputation in this
branch of engineering, was
appointed chief engineer. A
survey of the line was made in
the summer of 1869, and the
Brooklyn tower located. It was
while engaged in this work that
Mr. Roebling met with an
accident that resulted in his
death. In the same year his son,
Washington A. Roebling, was
appointed to the position
formerly occupied by his father,
and under his supervision the
work was carried to completion
in May, 1883.
In May, 1869, the War
Department, in compliance with
an act of Congress, appointed
Generals Wright and Newton and
Major King" a commission of
government engineers to examine
into the feasibility of the
project, and to report whether
the bridge would be an
obstruction to navigation. This
resulted in changing the clear
height to 135 feet above mean
high tide, and in widening the
bridge from 80 to 85 feet, in
order to provide a double
roadway on each side, In those
days it was not contemplated to
use the bridge for the passage
of ordinary street cars, but to
furnish it with a cable system
of its own. The importance of
the slight increase in width
mentioned can hardly be
overestimated, since it made
provision for the vehicle and
trolley traffic of the present
time. In June, 1874, an act was
passed changing the name to that
of the New York and Brooklyn
Bridge, and making it a public
work to be constructed by the
two cities, Brooklyn paying
two-thirds of the cost and New
York one-third.
The foundation of the Brooklyn
tower was begun in 1870. The
caisson, a rectangular chamber
102 feet wide by 168 feet long
and having a solid roof 15 feet
thick, was sunk to a depth of 44
1/2 feet. Brick piers were then
built in the air-chamber, which
was finally completely filled
with concrete. As the caisson
was sunk the granite masonry
forming the tower proper was
built above it. The New York
foundation was also carried to
solid rock, the caisson in this
case being slightly larger than
the other, 102 feet wide by 172
feet long. The cutting edges
were extended to a depth of 78
feet below mean high water, this
being necessary because of the
presence of extensive beds of
quicksand resting on the rock.
The roof was 22 feet thick and
was surmounted by a cofferdam
reaching to high water, thereby
increasing the buoyancy and
lessening the pressure on the
frames during sinking.
The towers are not solid masses
of masonry, but each is composed
of three buttressed shafts
joined together up to the
roadway by four connecting
walls. In the Brooklyn tower the
course of the walls next the
caisson is 17 feet thick; the
thickness diminishes by offsets
until at high water it is but 10
1/2 feet. This forms two well
holes which are filled with
concrete below water line and
left open from there to the
roadway. Spaces are also left
from 2 feet above the crown of
the arches to within 4 1/2 feet
of the top of the tower. Above
the roadway the tower consists
of three columns having an
oblong section; they are united
at the top by arches having a
span of 33 3/4 feet. Each arch
is formed by the intersection of
two arcs of circles having a
radius of 48 1-6 feet. Below the
water the masonry is largely
limestone, except the facing of
the two upper courses, which is
granite; the backing from high
water to the roadway is granite,
which constitutes all the
remainder of the tower. At the
towers the height of the roadway
is 119 1/4 feet, the top of the
towers being 272 feet from the
water. The height from the
bottom of the foundation to the
top is, in the Brooklyn tower,
316 feet, and in the other 349
feet. At high water mark the
towers measure 141 by 59 feet,
at the roadway 131 by 48, and at
the base of the cornice 126 by
43. The greatest pressure at any
point is in the tower masonry at
the base of the central shaft at
the roadway, where each square
foot supports about 26 tons.
At a distance of 930 feet from
each tower is an anchorage which
rests on timber grillage, and in
which the ends of the four
cables are anchored. Each
anchorage weighs 60,000 tons and
is built solid, with the
exception of tunnels or openings
for the passage of the cables.
Near the outside lower angle of
each anchorage are four anchor
plates (one for each end of each
cable), which are held down by
the dead weight of masonry piled
upon them. Each plate weighs 23
tons, and in shape resembles an
enormous wheel having a hub and
sixteen spokes. The connection
between the cable wires and the
plates is made with eye bars,
which start in double sets from
each plate, one curving over the
other, and are vertical for a
distance of about 25 feet, when
they curve about 90 degrees on a
circle having a radius of 49 1/2
feet. The bars have an average
length of 12 1/2 feet. The first
three sets have a section of 7
by 3 inches, the next three 8 by
3, the next three 9 by 3 inches;
the tenth set is double in
number and each bar is 1 1/2 by
9 inches in section.
Piercing
the center of the anchor plates
are two parallel sets of
apertures, each containing nine
holes. A bar is passed through
each hole and a 7-inch pin run
through the eyes or holes in the
end of each bar. These bolts
bear firmly against the under
side of the anchor plate, and
serve to distribute the strain
to every part of the plate. The
next series of bars is attached
to these by a bolt 5 feet in
length and 5 inches in diameter.
In this manner the succeeding
bars are united, forming a chain
having very long links connected
to each other by bolts passing
through the eyes. At each
knuckle of the chains a large
block of granite was placed with
a heavy cast iron plate inserted
as a bearing for the heads of
the links. The bars in the last
link are increased in number to
38, and are arranged in four
courses, one above the other.
The wires of the cable are
divided into 19 strands and each
strand is fastened around a
grooved eye-piece which is held
between two of the anchor bars.
The first work connected with
cable making was the passing of
a rope from one anchorage to the
other over the towers. By
August, 1876, an endless rope
had been placed from a driving
engine at the Brooklyn anchorage
to and around sheaves at the New
York anchorage.
The first operation, preliminary
to placing the cables in place,
was that of adjusting four
wires, one for each cable, to be
used as guides in obtaining an
exactly uniform deflection of
all the others. Four wires of
uniform size and weight were
selected. These were adjusted to
a tangent line for the land
spans, whose position had been
calculated, and to a level line
at the lowest point of the curve
for the center of the span.
Allowances were made for the
temperature prevailing at the
time.
The cables were made of
galvanized steel wires, No. 8,
Birmingham gauge. The strength
of the cables per square inch of
solid section is 160,000 pounds.
Each cable is composed of 19
strands, each of which contains
278 wires. The last wire of the
cables was run over October 5,
1878. At a distance of 21 1/2
feet, from the anchor bars heavy
clamps were put on the cables to
draw them to a cylindrical form.
This was made necessary as the
anchor bars spread so as to
cover a space 5 feet square. The
cables were finally wrapped with
galvanized iron wire, the
finished diameter being I5 3/4
inches.
On top of the towers the cables
rest in saddles which furnish a
bearing with easy vertical
curves. In plan they are
rectangular, 13 by 4 1-12 feet,
and have an extreme height at
the center of 4 1/2 feet and a
thickness of 4 inches. Each
cable passes over the center of
its saddle in a groove 19 1/2
inches wide by 17 1/2 inches
deep. The saddles rest on steel
rollers, which in turn rest on
planed plates. This permits the
cables to move freely backward
and forward, and to accommodate
themselves to any unequal
loading, and also to adapt
themselves to changes in
temperature.
Passing over the towers
alongside of the cables are 100
steel wire rope stays, arranged
25 to each cable, and secured at
each end to the trusses carrying
the floor system. The longest
extend to a distance of about
400 feet each side of the
towers, and are spaced 15 feet
apart at the trusses.
The floor system consists of six
longitudinal trusses connected
by floor beams, the whole being
hung from the cables by
suspender ropes. The suspender
ropes are of twisted galvanized
steel wire, and are from 1 5/8
to 1 3/4 inches in diameter.
Each is capable of sustaining
about 50 tons, or five times the
load it will ever be subjected
to. As the floor system is in a
continuous line from the top of
the anchorages, and as the
cables leave the anchorages a
few feet below, the floor beams
rest on the cables until the
latter rise above the grade. The
beams are here laid on posts
resting on the cables, which
vary in height to suit the
distances, and are braced by
plate brackets. The lower end of
each post is bolted to the upper
half of a strap encircling the
cable. The whole number of
suspender ropes is 1,520, and
the posts number 280. The floor
beams were made in half lengths,
and when riveted together at the
center formed a continuous beam
86 feet long. They are 32 inches
deep, 9f inches wide, and each
weighs 4 tons. Each has two top
and two bottom chords so united
as to form a triangular,
latticed girder. The chords are
of steel channel bars. The beams
are spaced 7 1/2 feet between
centers, and between each pair
is placed an I-beam, which rests
on the bottom truss chords, so
that the planking is supported
at every 3 3/4 feet. The work of
placing the floor beams was
begun at the towers, and carried
each way at the same time, in
order to load the cables
uniformly.
The bridge is divided by six
longitudinal trusses into five
passage ways, the trusses being
of the following heights,
measured from the top of the
floor beams: The two outside
ones 7 1/2 feet, and the four
intervening ones 15 feet 7 1/2
inches. Across the central
opening is a system of light
beams supporting the promenade,
which is 12 feet above the floor
beams. The roadways at the
outside are 18 3/4 feet wide in
the clear, and although only
designed for vehicles, each now
has a trolley track. The two
remaining divisions are 12 2-3
feet wide in the clear, and are
used for passenger cars. As the
foot passenger approaches the
towers he ascends a few steps,
the walk dividing and passing
through each of the tower arches
on a flooring laid on the beams
over the car tracks.
To prevent horizontal vibrations
and to resist the force of the
wind, there are wind braces
placed beneath the floor beams.
These are steel wire ropes from
2 to 3 inches in diameter, and
are anchored at the four facing
corners of the towers to eye
bolts set in the masonry. From
the corners to which they are
attached they pass diagonally
across the floor beams to the
opposite side of the bridge,
where they are secured. The
longest ones reach about half
way across. Similar braces are
provided on the short spans. As
a further precaution, and
particularly to secure stability
at the center of the span, where
the braces are of little effect,
the outside cables are drawn in
a short distance toward the
center. To allow for expansion
and contraction of the trusses,
slip joints are formed between
the towers and anchorages and in
the main span. The aggregate
weight of the suspended
structure, including cables,
trusses, suspenders, braces,
timber flooring, and rails, is
14,680 tons ; the estimated
transitory load is 3,100 tons,
making the total weight of the
superstructure 17,780 tons.
The Brooklyn approach is 971
feet long on the center line,
and is 1OO feet wide throughout.
It spans several streets by
plate girders, and has one curve
at about 200 feet from Sands
street. The New York approach is
1,562 1/2 feet long, begins at
grade at Park Row, and rises
3.25 feet per hundred to the
rear of the anchorage. It is 100
feet wide for about 500 feet of
the distance, and 85 for the
remainder. At Franklin Square is
an opening measuring 210 feet on
one side and 170 on the other,
which is spanned by a bridge.
The other streets are crossed by
semi-circular brick arches. Both
approaches consist of arches
resting on massive piers, the
fronts being entirely of
granite. The cornice over the
arches has a dentil course
below, surmounted by a heavy
projecting coping course. The
whole is capped by an ornamental
granite parapet. The arches are
used as stores and warehouses.
When the bridge was opened the
cars were moved by an endless
cable operated by engines
located beneath the Brooklyn
approach. This service soon
proved to be inadequate, and the
third-rail electric system was
introduced and is now in effect.
As a further improvement, and in
order to accommodate the travel
using the elevated roads of
Brooklyn, connection was made
with these loads so that the
passage of the bridge could be
made without change. In addition
to this a trolley track was laid
along each roadway in order that
all the trolley lines in the
Borough could cross the bridge
without interruption. All these
changes made necessary the
complete re-designing and
re-construction of the Brooklyn
approaches, and also the
changing of the station at the
western end.
The financial condition of the
bridge on March 31, 1883,
shortly before it was opened to
traffic, was stated as follows:
Cash received from New York
Cash received from Brooklyn
Cash received from rents,
interest, sale of material,
&c.,
Total: |
4,871,900.00
9,423,692.73
391,463.93
___________
$14,687,056.66
|
There is still due from the
City of New York, 216,666.66
And from Brooklyn, 433.333.34
Total cost of bridge,
$15,337,056.66
During the period occupied by
its erection New York was in the
clutches of the Tweed ring, an
audacious and unscrupulous gang
of thieves. Yet, when the
accounts were finally audited,
every dollar of the
appropriations was found to have
been expended in wages or
material, and its actual face
value was represented in the
completed structure. The ring
had proposed otherwise and the
belief was general that the
bridge treasury had been looted.
Mayor William C. Havemeyer
appointed a committee to
investigate the matter. Abram S.
Hewitt was a member of that
committee. In speaking of the
results of this inquiry, Mr.
Hewitt said: "
The duty was performed without
fear or favor. The methods by
which the ring proposed to
benefit themselves were clear
enough, but its members fled
before they succeeded in
reimbursing themselves for the
preliminary expenses which they
had defrayed. With their flight
a new era commenced, and during
the three years I acted as a
trustee I am sure that no fraud
was committed, and that none was
possible. Since that, time the
board has been controlled by
trustees, some of whom are
thorough experts in bridge
building, and the others men of
such high character that the
suggestion of malpractice is
improbable to absurdity. "
The bridge has not only been
honestly built, but it may be
safely asserted that it could
not now be duplicated at the
same cost. Much money might,
however, have been saved if the
work had not been delayed
through lack of means and
unnecessary obstacles interposed
by mistaken public officials.
Measured by its capacity and the
limitations imposed on its
construction by its relation to
the interests of traffic and
navigation, it is the cheapest
structure ever erected by the
genius of man."'
n a certain sense this bridge
was an experiment. That it would
largely eliminate the East River
as an obstacle to travel to and
from Brooklyn, and that it would
place the outlying districts of
that city at the door of New
York, were facts known and
appreciated by its promoters;
but whether the people would
avail themselves of the
increased facilities afforded
was a matter of freely expressed
doubts. To convince oneself that
the bridge has more than
fulfilled all the expectations
of its projectors, it is only
necessary to view the vast
multitudes that are continuously
passing across it. But the real
work it has accomplished can
best be ascertained by an
examination of the sections of
Brooklyn, formerly waste spaces,
that are now covered with the
homes of people, a large portion
of whom resort daily to New
York.
We have extended our notes on
the Brooklyn Bridge to
considerable length because of
its vast importance in providing
easy transit between sections of
the city that were separated by
a natural barrier, because it
was the first municipal
undertaking on the line of rapid
transit, and because the bridge
is beautiful to a degree as well
as useful. It is said to be the
most inspiring example of
suspended bridge construction in
the world. It is doubtful
whether it will be duplicated
anywhere in the future. Its
lofty towers and its graceful
span are visible to everyone who
enters our harbor. It is a
notable monument to the genius
of the engineers who planned it
and to the public spirit of
those citizens who, with
untiring zeal in the face of
great obstacles, so worked that
it was carried to completion. It
typified union between nearby
centers of unrelated population.
It has led to the conception of
that political union which has
made New York the second city on
the globe. It brought the men of
both sections into collaboration
for transportation facilities of
far wider scope and usefulness.